Industry Insights

Interxion and Telecity; spot the difference?
April 13, 2010
Interxion and Telecity; spot the difference?

With the release of Interxion’s 2009 results, we thought it might be interesting see how the two European headquartered operators might contrast and compare.  In fact it turned out to be quite hard to find any differences, though those that there are tell an interesting tale.


Telecity

Interxion

2009 Revenue (Euros, Millions)

192m, +27% (increase on 2008)

171m, +24%

Year End Capacity (sq m)

58,496

54,879

Capacity Added in 2009

7,084 sq m

11, 600 sq m

Capex Spend in 2009 (€)

100m

100m

Growth via existing customers

60%

70%

Number of Countries

7

11

Number of data centres

23

26

Customer Numbers

3500

1100


So, on most criteria the two companies are remarkably similar.  Apart from the fact that Interxion operate in four more countries than Telecity (Spain, Austria, Denmark and Switzerland, though worth pointing out that Telecity operate in Italy where Interxion don’t), the biggest difference between the two companies is in fact customer numbers, with Telecity claiming over three times the number of clients than Interxion.

Why might this be and what does it mean for customers today?  We think one of the reasons there is such a difference goes back to Telecity prior to the 2005 merger of Telecity and Redbus.  ITelecity 8&9 Harbour Exchangen particular, Redbus went to great efforts in its early days to attract smaller clients as exemplified by their simple pricing strategy (£4000 per annum or £350 per month per rack) and a customer friendly monthly rolling contract, somewhat harking back to the ISP background of Redbus founder Cliff Stanford, who had co-founded Demon Internet before selling out to Scottish Telecom in 1998.  Thus the Redbus sites that were rolled into the combined Telecity Group contained lots of smaller ISP and hosting clients.  A good example of this would be 6&7 Harbour Exchange in London’s Docklands.  Another factor behind the difference in client numbers will be the number of managed services customers that Telecity has, especially since its acquisition of the European operations of Globix in September 2006.  Globix added some 400 clients to the new group, hosted across their two London data centres.

In terms of meaning today we have the following views:  Each company creates a very similar product to similar standards (doubtless howls of protest to follow from each)!  However, the differences appear at a facility and regional level.  For example, its impossible to say who is the best or who has the best site; in our view the “best” is a very subjective criteria.  The best colo solution for client A may be useless for client B, for example if one is a telco looking to connect with other carriers whilst the other is a digital photo library looking for cheap kilowatts, the “best” solution would be completely different for each customer.   There are also differences in each location, for example London is clearly Telecity’s stronghold, with no less than eight separate data centres whilst in Paris though Interxion have expanded rapidly and have now launched their sixth site whilst Telecity have only just opened their second.   Newer facilities are easier to compare in some respects as you have essentially similarly specified facilities with no legacy network or customer base to attract clients with.  On the other hand in established sites the client and carrier mix can offer attractive opportunities even in spite of the disadvantages an older specification can sometimes entail such as limited power densities and its in these facilities where customer numbers matter more.   For example, if an 80,000 sq ft site only has a dozen or so installed clients then the implication would be the operator is focussing on a few reasonably large scale clients and might be less interested in a one rack only customer.  On the otherhand, if a facility has 100s of installed clients then clearly the facility and operator suits small scale clients and  furthermore, will probably offer a much more competitive marketplace for other products and services such as IP bandwidth.  As perhaps we might be expected to say, this is where market knowledge can really make the difference!  Matching buyers with both the right kind of operator with the right kind of facility is

One Response to “Interxion and Telecity; spot the difference?”

  1. [...] about two thirds of these companies’ growth comes from existing customers) and don’t forget our recent note about Telecity’s high customer count.  Indeed we have long felt that in acquiring IXEurope [...]

Related Posts

Telecity acquires Dublin's Data Electronics Group
August 8, 2011

Telecity has announced the acquisition of Dublin’s leading and longest established colocation provider Data Electronics Group.  The privately held company was bought for just under £90m and operates two data centres offering a combined capacity of 4600 sq m or about 4MW of customer power.  The two DE [...]

Telecity Powergate 2 update
March 23, 2011

We were able to take a look at progress on Telecity’s massive expansion to their Powergate, Park Royal facility.
Construction of the 21Mw extension to Powergate is now well underway with the first phase due for delivery in the third quarter of 2011.  The existing Powergate site which opened [...]

Latest Docklands Availability and News – Q4 2010
November 30, 2010

Overall occupancy in the Docklands area remains extremely high and list pricing at over £600 per kW per month expensive, but capacity can be found and deals are available if you know where to look!
Telehouse – interest in this key network hub remains unsurpassed.  Telehouse West, the new [...]

QuantHouse select Interxion London
May 24, 2010

QuantHouse, who provide ultra low latency trading solutions have added Interxion London to their London data center coverage.  QuantHouse clients include The London Stock Exchange, Credit Suisse and Turquoise. 

Interxion take first steps toward US IPO
May 7, 2010

Interxion have announced the draft filing of their F-1 form with the SEC, the first step in a possible US IPO of the company which Interxion say could take place in the second half of 2010.  The F-1 is a standard document used by foreign companies listing on [...]

Bull expand with Interxion Amsterdam
May 6, 2010

Interxion have announced the systems integrator and IT services provider Bull has expanded its data centre footprint with Interxion Netherlands.  Bull’s clients include DetailResult Services.

Telecity to triple capacity at Powergate
April 28, 2010

Telecity have announced the much anticiapated expansion at their Park Royal flagship facility Powergate.  But few would have anticipated the expansion would be an effective tripling of their capacity at this site.  An additional 20MW of client power is being made available across 10, 000 sq m of new space [...]

Financial Services Client win for Interxion Germany
April 20, 2010

Trade Haven GmbH, a company which provides trading platforms and systemsto banks, brokers, asset managers and traders has taken capacity at both Interxion Frankfurt and Dusseldorf.